Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloading
- Autores
- Agüero, Jorge Luis; Beroqui, Mario César; Di Pasquo, H.
- Año de publicación
- 2005
- Idioma
- inglés
- Tipo de recurso
- documento de conferencia
- Estado
- versión publicada
- Descripción
- This paper presents several modifications developed in a gas turbine control system. One of the modifications made in turbine control limits speed deviations to the governor. Consequently, this modification limits turbine power delivered -positive and negative- for Primary Control of Frequency purposes. In addition, this modification avoids that large, sudden power unloading takes place when the grid frequency recovers from a big dip, while original operational control modes are active. Together with complementary modifications made in the power plant centralized control, other turbine control modifications allow operators to adjust set points of grid frequency, dispatched power and required spinning reserve (positive and negative) which are established by the Dispatch Center of Argentinean electrical grid. Another modifications made in the power plant centralized control allows keeping the spinning reserve margins always available in spite of variations of maximum turbine power with weather conditions. These modifications were developed in a 120 MW gas turbine, which is part of a combined cycle in Tucumán, Argentina. Finally, several tests carried out on the turbine are presented together with operational records that were taken during system frequency disturbances. The tests and operational records show the behavior of the turbine power with and without the modifications made to its control system.
Instituto de Investigaciones Tecnológicas para Redes y Equipos Eléctricos (IITREE) - Materia
-
Ingeniería
Frequency
Frequency control
Gas turbines
Governors
Power generation availability
Power generation control
Power generation scheduling - Nivel de accesibilidad
- acceso abierto
- Condiciones de uso
- http://creativecommons.org/licenses/by-nc-sa/4.0/
- Repositorio
.jpg)
- Institución
- Universidad Nacional de La Plata
- OAI Identificador
- oai:sedici.unlp.edu.ar:10915/36737
Ver los metadatos del registro completo
| id |
SEDICI_8f1751abf99d4dec114bf064cab82971 |
|---|---|
| oai_identifier_str |
oai:sedici.unlp.edu.ar:10915/36737 |
| network_acronym_str |
SEDICI |
| repository_id_str |
1329 |
| network_name_str |
SEDICI (UNLP) |
| spelling |
Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloadingAgüero, Jorge LuisBeroqui, Mario CésarDi Pasquo, H.IngenieríaFrequencyFrequency controlGas turbinesGovernorsPower generation availabilityPower generation controlPower generation schedulingThis paper presents several modifications developed in a gas turbine control system. One of the modifications made in turbine control limits speed deviations to the governor. Consequently, this modification limits turbine power delivered -positive and negative- for Primary Control of Frequency purposes. In addition, this modification avoids that large, sudden power unloading takes place when the grid frequency recovers from a big dip, while original operational control modes are active. Together with complementary modifications made in the power plant centralized control, other turbine control modifications allow operators to adjust set points of grid frequency, dispatched power and required spinning reserve (positive and negative) which are established by the Dispatch Center of Argentinean electrical grid. Another modifications made in the power plant centralized control allows keeping the spinning reserve margins always available in spite of variations of maximum turbine power with weather conditions. These modifications were developed in a 120 MW gas turbine, which is part of a combined cycle in Tucumán, Argentina. Finally, several tests carried out on the turbine are presented together with operational records that were taken during system frequency disturbances. The tests and operational records show the behavior of the turbine power with and without the modifications made to its control system.Instituto de Investigaciones Tecnológicas para Redes y Equipos Eléctricos (IITREE)2005-07info:eu-repo/semantics/conferenceObjectinfo:eu-repo/semantics/publishedVersionObjeto de conferenciahttp://purl.org/coar/resource_type/c_5794info:ar-repo/semantics/documentoDeConferenciaapplication/pdfhttp://sedici.unlp.edu.ar/handle/10915/36737enginfo:eu-repo/semantics/openAccesshttp://creativecommons.org/licenses/by-nc-sa/4.0/Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International (CC BY-NC-SA 4.0)reponame:SEDICI (UNLP)instname:Universidad Nacional de La Platainstacron:UNLP2025-10-22T16:41:09Zoai:sedici.unlp.edu.ar:10915/36737Institucionalhttp://sedici.unlp.edu.ar/Universidad públicaNo correspondehttp://sedici.unlp.edu.ar/oai/snrdalira@sedici.unlp.edu.arArgentinaNo correspondeNo correspondeNo correspondeopendoar:13292025-10-22 16:41:09.285SEDICI (UNLP) - Universidad Nacional de La Platafalse |
| dc.title.none.fl_str_mv |
Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloading |
| title |
Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloading |
| spellingShingle |
Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloading Agüero, Jorge Luis Ingeniería Frequency Frequency control Gas turbines Governors Power generation availability Power generation control Power generation scheduling |
| title_short |
Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloading |
| title_full |
Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloading |
| title_fullStr |
Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloading |
| title_full_unstemmed |
Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloading |
| title_sort |
Gas turbine control : Modifications for: availability and limitation of spinning reserve and limitation of non-desired unloading |
| dc.creator.none.fl_str_mv |
Agüero, Jorge Luis Beroqui, Mario César Di Pasquo, H. |
| author |
Agüero, Jorge Luis |
| author_facet |
Agüero, Jorge Luis Beroqui, Mario César Di Pasquo, H. |
| author_role |
author |
| author2 |
Beroqui, Mario César Di Pasquo, H. |
| author2_role |
author author |
| dc.subject.none.fl_str_mv |
Ingeniería Frequency Frequency control Gas turbines Governors Power generation availability Power generation control Power generation scheduling |
| topic |
Ingeniería Frequency Frequency control Gas turbines Governors Power generation availability Power generation control Power generation scheduling |
| dc.description.none.fl_txt_mv |
This paper presents several modifications developed in a gas turbine control system. One of the modifications made in turbine control limits speed deviations to the governor. Consequently, this modification limits turbine power delivered -positive and negative- for Primary Control of Frequency purposes. In addition, this modification avoids that large, sudden power unloading takes place when the grid frequency recovers from a big dip, while original operational control modes are active. Together with complementary modifications made in the power plant centralized control, other turbine control modifications allow operators to adjust set points of grid frequency, dispatched power and required spinning reserve (positive and negative) which are established by the Dispatch Center of Argentinean electrical grid. Another modifications made in the power plant centralized control allows keeping the spinning reserve margins always available in spite of variations of maximum turbine power with weather conditions. These modifications were developed in a 120 MW gas turbine, which is part of a combined cycle in Tucumán, Argentina. Finally, several tests carried out on the turbine are presented together with operational records that were taken during system frequency disturbances. The tests and operational records show the behavior of the turbine power with and without the modifications made to its control system. Instituto de Investigaciones Tecnológicas para Redes y Equipos Eléctricos (IITREE) |
| description |
This paper presents several modifications developed in a gas turbine control system. One of the modifications made in turbine control limits speed deviations to the governor. Consequently, this modification limits turbine power delivered -positive and negative- for Primary Control of Frequency purposes. In addition, this modification avoids that large, sudden power unloading takes place when the grid frequency recovers from a big dip, while original operational control modes are active. Together with complementary modifications made in the power plant centralized control, other turbine control modifications allow operators to adjust set points of grid frequency, dispatched power and required spinning reserve (positive and negative) which are established by the Dispatch Center of Argentinean electrical grid. Another modifications made in the power plant centralized control allows keeping the spinning reserve margins always available in spite of variations of maximum turbine power with weather conditions. These modifications were developed in a 120 MW gas turbine, which is part of a combined cycle in Tucumán, Argentina. Finally, several tests carried out on the turbine are presented together with operational records that were taken during system frequency disturbances. The tests and operational records show the behavior of the turbine power with and without the modifications made to its control system. |
| publishDate |
2005 |
| dc.date.none.fl_str_mv |
2005-07 |
| dc.type.none.fl_str_mv |
info:eu-repo/semantics/conferenceObject info:eu-repo/semantics/publishedVersion Objeto de conferencia http://purl.org/coar/resource_type/c_5794 info:ar-repo/semantics/documentoDeConferencia |
| format |
conferenceObject |
| status_str |
publishedVersion |
| dc.identifier.none.fl_str_mv |
http://sedici.unlp.edu.ar/handle/10915/36737 |
| url |
http://sedici.unlp.edu.ar/handle/10915/36737 |
| dc.language.none.fl_str_mv |
eng |
| language |
eng |
| dc.rights.none.fl_str_mv |
info:eu-repo/semantics/openAccess http://creativecommons.org/licenses/by-nc-sa/4.0/ Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International (CC BY-NC-SA 4.0) |
| eu_rights_str_mv |
openAccess |
| rights_invalid_str_mv |
http://creativecommons.org/licenses/by-nc-sa/4.0/ Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International (CC BY-NC-SA 4.0) |
| dc.format.none.fl_str_mv |
application/pdf |
| dc.source.none.fl_str_mv |
reponame:SEDICI (UNLP) instname:Universidad Nacional de La Plata instacron:UNLP |
| reponame_str |
SEDICI (UNLP) |
| collection |
SEDICI (UNLP) |
| instname_str |
Universidad Nacional de La Plata |
| instacron_str |
UNLP |
| institution |
UNLP |
| repository.name.fl_str_mv |
SEDICI (UNLP) - Universidad Nacional de La Plata |
| repository.mail.fl_str_mv |
alira@sedici.unlp.edu.ar |
| _version_ |
1846782897324818432 |
| score |
12.982451 |